Case study
Baranduda Fields
Baranduda Fields opened in August 2024 with new football, cricket and netball facilities. It is also the first delivered stage of a 25-year sporting precinct that has been repeatedly reimagined since 2000. What, exactly, has Wodonga built—and what remains a plan?
What exists now
On a Saturday at Baranduda Fields, the answer is plainly useful: two NPL-standard football pitches, a full-size AFL/cricket oval, two netball courts, two pavilions, paths, lighting and car parking. The football pavilion has grandstands for 448 and 192 people; the sealed car park has 362 ordinary spaces and eight accessible spaces. The precinct opened on Thursday 8 August 2024.
That is a substantial public facility, and it should not be described away. But it is not the whole project that Wodonga has been planning on this roughly 100-hectare Council-owned site at 200 Baranduda Boulevard.
The gap matters because the place is now listed under Council’s “Completed Projects”, while the adopted 2018 masterplan remains a much larger, long-range proposition. Its GST-exclusive indicative estimate was $122.385 million. That was not a budget, an appropriation or a bill to be paid. It was a consultant’s estimate for services plus three stages. The 2018 Stage 1A schedule included two football/cricket ovals, two netball courts, a pavilion, car parks and the entry road; Stage 1B included the soccer precinct. What Council ultimately delivered as Stage 1 was reconfigured: one AFL/cricket oval and the two netball courts, plus two soccer fields and a soccer pavilion brought forward from Stage 1B, with the supporting services, paths, lighting and parking. The remaining major facilities in the 2018 staging scheme have not commenced construction, although later planning has continued. The 2018 stakeholder record helps explain—but does not by itself establish the cause of—that change: Football Federation Victoria asked Council to reprioritise soccer into Stage 1 and Murray United sought an early permanent base, while Wodonga Athletics Club and Wodonga Little Athletics recorded little interest in relocating and Softball Victoria described the proposed provision as a “backwards step”.
Football Federation Victoria
Sought earlier soccerAsked Council to reprioritise soccer into Stage 1.
Murray United
Sought an early baseSought an early permanent base at the precinct.
Wodonga Athletics Club · Wodonga Little Athletics
Low interest in relocatingRecorded little interest in relocating to Baranduda Fields.
Softball Victoria
ObjectedDescribed the proposed provision as a “backwards step”.
This is not simply a story about an unfinished sports complex. Large growth-area infrastructure is commonly staged. It is a story about how a single site came to carry several plans, several names and several funding systems—and how difficult the public record makes it to see the relationship between the facility residents can use and the larger project still being described.
A project older than its public shorthand
Council’s consultant says the original Baranduda Fields masterplan was prepared in 2000, then revised in 2007 and 2012. Council says it purchased the land in 2012, although the acquisition record itself has not been located. In early 2012 it established a Baranduda Fields Reference Group; its re-formed independent group met from May to October 2013.
- 2000Original masterplan prepared, per Council’s consultant
- 2007 · 2012Masterplan revised; Council says it purchased the land in 2012
- 2013Reference group endorses a 25-year staged concept plan
- Dec 2018Spiire masterplan adopted by Council
- 4 Apr 2019PSP and DCP take statutory effect (C121wdon gazetted)
- 8 Aug 2024Stage 1 opens
- Apr 2026Post-opening planning continues — synthetic-pitch planning grant
That 2013 process was more than a logo on a consultation page. More than 25 sporting and community groups were engaged over eight weeks, after letters to more than 50 associations; it produced 12 written submissions and a public forum. The group endorsed a 25-year staged enhanced concept plan. It also recorded a concern that support for existing grounds could diminish once Baranduda Fields was developed, and warned that the proposed timing for soccer, rugby and indoor sports did not necessarily match demand.
The group recommended a standing governance committee and separate work on sport, commercial and community interests capable of attracting capital or operational investment. No such committee or report has been located in the published material examined. That is a public-record limit, not proof that neither ever existed.
The most memorable early line has outlived its own purpose. Council’s current project page still says Baranduda Fields “will be the largest regional sporting precinct between Sydney and Melbourne”. The 2018 masterplan says this was the vision adopted in 2012. It also records that a 2016 workshop reached general consensus that the wording no longer reflected Council’s or the community’s vision, and replaced it. The old claim is a superseded vision statement—not an independently measured fact.
“will be the largest regional sporting precinct between Sydney and Melbourne”SUPERSEDED COUNCIL VISION · HISTORIC PROMOTIONAL LANGUAGE — adopted as the vision in 2012; a 2016 workshop reached general consensus the wording no longer reflected Council’s or the community’s vision, and replaced it. The phrase remains on Council’s current project page.
Three plans, three schedules
The central planning difficulty arrived in 2018.
The final Leneva–Baranduda Precinct Structure Plan and Development Contributions Plan are dated October 2018, but they took statutory effect when Amendment C121wdon was gazetted on 4 April 2019. The PSP is statutory planning. The DCP is the instrument that sets development contributions. The DCP was later amended in December 2023 through statewide Amendment VC249, which took effect on 15 January 2024 and exempted small second dwellings from existing development-contribution plans. In December 2018, Council adopted the Spiire Baranduda Fields Master Plan, a Council plan rather than a statutory instrument.
Leneva–Baranduda Precinct Structure Plan
Statutory planning frameworkReproduces the earlier reference-group concept: four soccer grounds plus a principal pitch, 12 tennis courts, six outdoor and two covered netball courts, three rugby grounds, two hockey pitches, an indoor stadium and four bowling greens.
Development Contributions Plan
Statutory contribution scheduleA narrower project description in places: two soccer pitches, eight tennis courts and an indoor stadium among other works. The schedule developers pay toward — subject to subdivision, demand and DCP funding — not a construction program.
Spiire Baranduda Fields Master Plan, 2018
Council-adopted non-statutory masterplanA three-pitch soccer facility, four local tennis courts, two Stage 1A netball courts with two more in Stage 2, and a different staging sequence.
They do not describe the same future facility. The PSP reproduces the earlier reference-group concept: four soccer grounds plus a principal pitch, 12 tennis courts, six outdoor and two covered netball courts, three rugby grounds, two hockey pitches, an indoor stadium and four bowling greens. The DCP’s project description is narrower in places: two soccer pitches, eight tennis courts and an indoor stadium among other works. The Spiire plan has a three-pitch soccer facility, four local tennis courts, two Stage 1A netball courts with two more in Stage 2, and a different staging sequence.
No public reconciliation document has been found. That does not make any one schedule fraudulent or meaningless. It does mean there is no honest single “original plan” against which to announce a percentage delivered. They are related plans with different functions, dates and levels of detail. The DCP is especially important because it is the schedule developers pay toward, subject to subdivision, demand and DCP funding—not because it is a construction program.
The site itself resists simple arithmetic. The masterplan describes more than 100 hectares. The PSP’s open-space guide counts 66.5 hectares of active open space. The native-vegetation plan identifies 51.4 hectares of Category 1 developable land, 0.9 hectares of vegetation-protection land within the development area and 29.7 hectares of adjoining WREN conservation land. Middle Creek, native vegetation and a retained scar tree are part of the project’s physical constraints. None of these figures can be substituted for another.
How Stage 1 was funded—and what was not spent
The funding history also takes more than one date.
The Commonwealth commitment was announced during the April 2019 federal election campaign, included in the 2019–20 Federal Budget, formally approved on 8 December 2019 as funding “up to” $10 million under the Community Development Grants Program, and put into a funding agreement on 23 March 2020. Council managed delivery.
- Apr 2019Announced during the federal election campaign
- 2019–20Included in the Federal Budget
- 8 Dec 2019Formally approved — “up to” $10 million, Community Development Grants Program
- 23 Mar 2020Funding agreement executed
- 2020–2024Council-managed delivery, to the August 2024 opening
Council publicly describes Stage 1 as a $24 million project funded by $10 million from the Commonwealth and a rounded $14 million Council contribution. In evidence to the Victorian Parliament on 4 September 2024, Council’s chief executive also identified a $24,000 Victorian Government contribution, with the remainder funded by Council. Those records operate at different levels of precision: the $14 million figure is public shorthand, not a verified exact Council residual, and the final capital ledger has not been recovered. The $24 million figure is therefore best treated as the published Stage 1 project envelope, not verified final actual expenditure. In February 2022 Council redirected $2 million in unbudgeted land-sale proceeds to Stage 1 and added $225,000 to the civil contract.
$24m — delivered Stage 1 project envelope
- Published funding account: up to $10m Commonwealth plus a rounded $14m Council contribution
- $24,000 Victorian Government contribution, identified in 2024 parliamentary evidence
- $2m unbudgeted land-sale proceeds redirected to Stage 1, February 2022, and $225,000 added to the civil contract
- Final actual expenditure and the exact funding reconciliation: not recovered
$122.385m ex GST — indicative whole-masterplan estimate
- A consultant’s GST-exclusive estimate for services plus three stages
- Not a budget, not an appropriation, not the Stage 1 cost
$20.306m — DCP provision for two site projects
- $14.881m construction works and $5.425m indoor stadium
- Contingent, growth-paced levy program — not cash already available, not money already spent
Wider Leneva–Baranduda DCP accounting
- $5.273m restricted DCP reserve in the 2024–25 accounts
- $5.056m non-current DCP liability — future settlement and works-in-kind obligations
- Neither balance is publicly attributed to Baranduda Fields as project spend
Those figures concern the delivered first stage. They must not be added to the $20.306 million listed in the DCP for two Baranduda Fields projects: $14.881 million for construction works and $5.425 million for an indoor stadium. That is a contingent, growth-paced levy program, not cash already available to the complex and not evidence of money already spent there.
Council’s 2024–25 accounts record $5.273 million in the wider Leneva–Baranduda DCP restricted reserve and, separately, a $5.056 million non-current Leneva–Baranduda DCP liability associated with future settlement and works-in-kind obligations. The published accounts do not attribute any part of either balance to Baranduda Fields. They cannot prove the site has—or has not—received DCP money.
The $122.385 million masterplan estimate belongs in a third category again: an indicative whole-plan estimate, GST exclusive. Its detailed figures reconcile to that total, although a summary table elsewhere in the adopted plan contains internal arithmetic and stage-total inconsistencies. It was never a $122 million appropriation.
Delivery, then a quieter next phase
The first construction contracts made the delivery visible: plantation removal in late 2020, civil works in 2021, the soccer pavilion in 2022, then lighting, irrigation, fencing, sand and the AFL/netball pavilion. Council opened the precinct in August 2024. A later $50,000 Tiny Towns Fund grant was approved for grandstand seating; the State’s 2024–25 delivery table records $25,000 net delivered. In April 2026 the State announced a separate $37,500 grant for synthetic-pitch planning—not construction.
The later stages in the 2018 adopted masterplan remain unbuilt, but their layout was not frozen in 2018. That plan’s Stage 1B included an indoor highball facility, tennis, playground, three soccer pitches, a water body, café, criterium circuit and treatment plant; Stage 2 included athletics, bowls, hockey, rugby, baseball/softball and more netball; Stage 3 multi-purpose grassed fields. In January 2021 Council released an updated site layout after environmental and flood modelling: the entry and car parks were reconfigured, the soccer precinct moved further west, tennis, lawn bowls, the athletics track and highball facility were relocated, and the criterium circuit was removed while wetlands management was investigated. The 2018 stage list is therefore a record of the adopted plan, not an unchanged current construction schedule.
2018 adopted masterplan — the later stages as scheduled
- Stage 1B: indoor highball facility, tennis, playground, three soccer pitches, a water body, café, criterium circuit and treatment plant
- Stage 2: athletics, bowls, hockey, rugby, baseball/softball and more netball
- Stage 3: multi-purpose grassed fields
January 2021 updated layout — after environmental and flood modelling
- Entry and car parks reconfigured
- Soccer precinct moved further west
- Tennis, lawn bowls, the athletics track and the highball facility relocated
- Criterium circuit removed while wetlands management was investigated
Council’s FAQ says further planning will occur before future implementation. No public decision has been located that abandons the later stages. Calling them abandoned would go beyond the evidence; calling the whole masterplan complete would do the same.
Stage 1 facilities
DeliveredOpened 8 August 2024 and in use.
Synthetic-pitch work
Planning / further investigationA $37,500 State planning grant announced April 2026 — planning, not construction.
Later-stage facilities
UnbuiltThe remaining major facilities in the 2018 staging scheme have not commenced construction.
Formal status of the later stages
No abandonment decision locatedCouncil’s FAQ says further planning will occur before future implementation; no public decision abandoning the later stages has been located.
The public disclosure is thinner than the scale of the site. The procurement register carries 90 lines naming Baranduda from 2022 to 2026, but only two publish a value: $264,750.49 for depot portable carpentry works and $389,689 for a Boyes Road shared path. A September 2023 line is titled “Baranduda Fields Sports Pavilion – Contractor Disputes”, with no value or public explanation. That is a disclosure characteristic of the register, not evidence of fault, cost or outcome.
There is a useful distinction here. The completed-project label is accurate for the facility Council opened. It is incomplete as an explanation of the broader adopted masterplan and statutory growth-area framework. The resident question is not whether a real sports complex exists. It does. It is whether Council will make it easier to understand which future components remain policy, which are being planned, which are funded, and which have entered a construction commitment.
For a precinct planned since 2000, that distinction is the difference between a promising map and a public account.
What was delivered, and what is unresolved
What has been delivered
- Opened: 8 August 2024.
- Two NPL-standard football fields; AFL/cricket oval; two netball courts; two pavilions; shared paths and car parks.
- Football pavilion seating: 448 and 192. Car parking: 362 standard and eight accessible spaces.
Keep these figures separate
The unresolved public-record questions
- No located public reconciliation of the PSP, DCP and 2018 masterplan facility schedules.
- No located decision explaining the status of Stage 1B or later stages beyond “further planning”.
- No public project-level attribution of DCP reserve money or works-in-kind to Baranduda Fields.
- No located acquisition record, governance-committee record, pavilion-dispute detail or outcome of the 2024 storage-facility grant application.
The record behind this page
The masterplan decisions and the whole construction tender chain are minuted Council resolutions held in the Council Record. The records are grouped by the question they answer.
The plan and its revision
The construction tender chain
Every Stage 1 award below is a minuted resolution, including the four let in the middle of the $20m→$24m reforecast window.
- Plantation removal (W2190-20) — 21 December 2020
- Stage 1 civil works (W2282-21) — 19 July 2021
- Soccer pavilion construction (W2598-21) — 21 February 2022
- Fencing and concreting — 27 June 2022
- Sports-field lighting — 27 June 2022
- Supply of sand — 27 June 2022
- Irrigation supply and installation — 27 June 2022
- AFL/Netball pavilion construction (W2850-22Q) — 20 September 2022
Other documents cited in this story
- The doors to the Baranduda Fields Sporting Complex open to the publicWodonga Council · 8 August 2024
- Baranduda Fields Sporting Complex — completed-project page and timelineWodonga Council · current
- Baranduda Fields FAQsWodonga Council · current
- Draft Baranduda Fields Master Plan — 2018 consultationWodonga Council · 2018
- Statement on Baranduda FieldsWodonga Council · 1 May 2019
- Leneva–Baranduda Development Contributions Plan (2018)Wodonga Council / Victorian Government · 2018Not in the Wodonga Wire source register
- Council welcomes $10m for Baranduda Fields projectWodonga Council · 19 April 2019
- Work set to start on new soccer pavilionWodonga Council · May 2022
- Draft Budget 2022–23 and Financial Plan — consultation archiveWodonga Council · 2022
- Baranduda Fields progress emerges from the groundWodonga Council · 14 July 2022
- Baranduda Fields pavilion tender awardedWodonga Council · 2020
- Baranduda Fields plan updated, works begin on siteWodonga Council · 21 January 2021
- Baranduda Fields — plantation removal project pageWodonga Council · current
- Approved planning stream — Baranduda Fields Synthetic Pitch PlanningSport and Recreation Victoria · 2026Not in the Wodonga Wire source register
This page is a Wodonga Wire derived record. It assembles published Council decisions, government and proponent documents and independent reporting into one account, and states where the public record does not settle a question. It is not a Council publication. Where no record is shown, none has been located — that is not the same as none existing.